Stay informed with regular updates on the progress of DRA Astra. We are committed
to delivering your home on time, maintaining the highest standards of
quality throughout every phase of construction.
July 2025
June 2025
May 2025
April 2025
March 2025
February 2025
TOP VIEW
Main building – Pour 1 1st lift Column Reinforcement work (99/127 no's)
Main building – Pour 1 1st lift column shuttering work (94/127 no's)
Main building – Pour 1 1st lift column concrete completed (94/127 no's)
Main building – Pour 01 DPC protective plastering work completed