Stay informed with regular updates on the progress of DRA DownTown. We are committed
to delivering your home on time, maintaining the highest standards of
quality throughout every phase of construction.
July 2025
June 2025
May 2025
April 2025
South East Overall Top View
Front View
Stilt floor Pour 1 roof slab shuttering work completed (1475/1475 Sqm) – 100% completed
Stilt floor Pour 1 roof reinforcement work completed (45/45 MT) – 100% completed
Stilt floor Pour 1 PT Strand placing work completed (05/05 MT) – 100% completed